BANGKOK SUBWAY NEWS - MARCH
2000-JANUARY 2001
January 2001
Updates from Thai Newspapers
translated and summarized by Wisarut Bholsithi
Demolishing Ratchada-Lad Phrao Flyover
to Rebuild the New One
Dailynews, January 24, 2001
MRTA is preparing to demolish the Ratchada-Lad Phrao Flyover and
rebuild a new one at the center of Ratchadaphisek Inner Ring Road since
the old one violates traffic engineering principle and is not safe. Furthermore,
the foot of flyover blocks the entry to the park and ride.
Mr. Praphat Jiongsa-nguan (MRTA Director) said MRTA is cooperating with
BMA and ION Joint Venture (MRTA Contractor) to demolish the Ratchada-Lad
Phrao since the flyover was built without using traffic engineering principles.
The flyover is on the left and right sides of the road, not at the center
as other flyovers. The reason is that the flyover was built when there
was a plan to construct the Lavalin Skytrain along Ratchadaphisek Inner
Ring Road in 1984. Therefore, BMA decided to construct a flyover on either
side of the road. However, Lavalin Skytrain was aborted since Lavalin
could not find financial resources to realize the project.
MRTA is constructing a subway along the old Lavalin route and found that
the flyover will block the entry of the park and ride facility (a 9-floor
building). The blueprint of the parking facility stipulates that it is
necessary to demolish the old flyover and build a new one at the center
of the road with a ramp connecting the flyover with the park and ride.
The budget for park and ride is about 100 million baht (US$ 2.5 million)
which MRTA will pay first and then BMA have to pay MRTA back. MRTA will
cut down the support pillars of the flyover so the tunnel can be built
without interruption on the flyover structure. Such a process will speed
up the construction since there is no need to wait until the flyover is
demolished and postpone the demolition process.
MRTA is now preparing the demolition of the flyover to be ready by the
end of the year and MRTA will ask Traffic Police to plan for traffic management
to minimize the demolition effects on the people.
MRTA Tunnel Construction
On Schedule
Thairath, January 4, 2001
Mr. Praphat Jongsa-nguan (MRTA Director) said that the construction of
the subway tunnel has met the schedule set by MRTA even though it was
initially delayed due to the problems with land transfer. There is 200
meters more to be done (from Samyan to Hua Lamphong) and the tunnel will
be done in this February, after 3 1/2 years of tunnel construction (started
in August 1997 at Bon Kai). The internal structure of 18 subway stations
is done, only the internal decoration (laying tracks, installation of
escalators and elevators, and setting up subway systems) is left to be
done.
Mr. Praphat said that there are three civil engineering sections that
need to be sped up to be completed on time (Northern section to be opened
on December 5, 2002, and Southern Section to be opened on August 12, 2003).
Three civil engineering sections to be sped
up:
1. Ventilation systems
2. Eight emergency exits at the following places
---2.1 Chula Soi 5 (between Sam Yarn and Hua Lamphong Station)
---2.2 Between Queen Sirikit and Sukhumvit Station
---2.3 Front of BB Tower between Sukhumvit and Phetburi Station
---2.4 Front of People Republic of China Embassy, just before Tiam Ruam
Mit Station
---2.5 Front of Robinson Department Store - Ratchada Branch (between Tiam
Ruam Mit and Pracharat Bumphen Station)
---2.6 Front of Nikko Mahanakhorn Hotel - now Grand Hotel after changing
the ownership (between Pracharat Bumphen and Suthisarn Station)
---2.7 Front of Panaphan school (between Lad Phrao and Phahol Yothin Station)
---2.8 Chatuchak Park (between Phahol Yothin and Mochit Station)
3. Tunnels across Suthisarn and Huay Kwang Intersection
Structure of 18 Subway
Stations Nearly Done
Thairath, January 15, 2001
Mr. Chookiat Phothayanuwat (Director Construction Dept., MRTA) said the
civil work section and the foundation work of 18 stations is nearly done.
| Civil Engineer Work |
Done |
| Northern Tunnel (Bangsue - Huay
Kwang) |
100% |
| Southern Tunnel (Huay Kwang - Hua
Lamphong) |
95% |
Station Foundation Works of Southern Section
Hua Lamphong Station
Station Roof ----100%
Ticket Floor ----100%
Sam Yarn Station
Station Roof ----97%
Ticket Floor ----94%
See Lom Station
Station Roof ----92%
Ticket Floor ----100%
Lumphinee Station
Station Roof ----100%
Ticket Floor ----100%
Bon Kai Station
Station Roof ----100%
Ticket Floor ----100%
Queen Sirikit Station
Station Roof ----100%
Ticket Floor ----100%
Sukhumvit Station
Station Roof ----97%
Ticket Floor ----100%
Phetburi Station
Station Roof ----99%
Ticket Floor ----98%
Rama IX Station
Station Roof ----91%
Ticket Floor ----100%
Stairways ----100%
Ventilation System ----50%
Station Foundation Works of Northern Section
Tiam Ruam Mit Station
Station Roof ----100%
Ticket Floor ----Not Done yet
Passenger Floor ----97%
4 Stairways ----Not Done yet
Pracharat Bumphen Station
Station Roof ----100%
Ticket Floor ----100%
Passenger Floor 100%
Tunnel at Huay Kwang Intersection
Digging Tunnel ----41%
Concrete Work ----38%
Suthisarn Station
Station Roof ----92%
Ticket Floor ----100%
Passenger Floor ----100%
Tunnel at Suthisarn Intersection
Digging Tunnel ----45%
Concrete Work ----38%
Ratchada Station
Station Roof ----100%
Ticket Floor ----100%
Passenger Floor ----100%
Lad Phrao Station
Station Roof ----100%
Ticket Floor ----100%
Passenger Floor ----100%
4 Stairways ----Not Done yet
Phahol Yothin Station
Station Roof ----100%
Ticket Floor ----100%
Passenger Floor ----100%
5 Stairways ----Not Done yet
Mochit Station
Station Roof ----100%
Ticket Floor ----100%
Passenger Floor ----85%
Platform Floor ----91%
2 Stairways ----Not Done Yet
Tunnel to go across Phahol Yothin Rd. ----Not Done yet
Kamphaengphet Station
Station Roof ----Not Done yet
Ticket Floor ----Not Done yet
Passenger Floor ----91%
3 Stairways ----Not Done Yet
Bangsue Station
Station Roof ----100%
Ticket Floor ----100%
Passenger Floor ----100%
2 Stairways ----Not Done Yet
Ventilation System on Footpaths ----Not Done yet
Ventilation System on the Middle Islets ----100%
5 Ventilation Chimneys ----Not Done yet
December 2000
Updates from Thai Newspapers
translated and summarized by Wisarut Bholsithi
Reducing BMTA buses running parallel to the
subway
Thairath Daily, December 11, 2000
Mr. Praphat Jong-sanguan, MRTA Director, said
MRTA has hired Mushell Co. Ltd. as a consultant company to study the system
connecting the MRTA Blueline with other modes of public mass transit with
an expenditure of 70 million baht and an 18-month study period.
The company started its work last September. Now the consultants
are studying the details of the connecting systems including BTSC Skytrain
since OCMLT made a new estimation that the daily passenger of MRTA blue
would be about 300,000 passengers a day instead of the previous estimation
of 400,000 passengers a day. Without good connecting systems, the
MRTA will have serious problems. The company will finish the preliminary
report in
January 2001 and MRTA will use this preliminary report to discuss with
other relating bureaus.
Mr. Wijit Wacharin, MRTA Deputy of Planning and
Development Engineering, said it is necessary to readjust the bust routes.
If the bus routes run parallel to MRTA for more than 10 stations, the
bus routes must be readjusted to prevent the wasteful competition.
After the preliminary discussion with BMTA, both MRTA and BMTA agreed
to readjust the parallel routes.
Mr. Pheeraphongse Issaraphakdee, BMTA Director,
said he agrees in principle to readjust the routes if BMTA buses run parallel
to MRTA Blue line for more than 10 stations. However, he does not mean
that BMTA will eliminate those bus routes since passengers would never
accept this due to the fact that bus tickets are much cheaper than subway
tickets. The BMTA director told the MRTA director that route readjustment
means the improvement of the connecting system. The subway entries should
allow buses to park nearby to facilitate the exchange of passengers in
a hassle-free manner. BTSC Skytrain does not allow BMTA buses to park
nearby the stairs causing lots of hassle and cutting down many potential
Skytrain passengers.
Commentary by Wisarut: It would be much
easier for BMTA to move the bus to closed to the Skytrain and Subway entries
than moving the stairs to BMTA bus stops.
Installing telecommunication network before
opening subway services to allow using mobile phone use in tunnels
Dailynews, December 13, 2000
Mr. Praphat Jong-sanguan, MRTA
Director, said mobile phone concession holders came to discuss with MRTA
since lots of people feel worried that they cannot use mobile phones inside
a tunnel 20 meters below ground level. MRTA said there is no need
to worry since MRTA is going to make a detailed discussion with mobile
phone companies and BMCL Co. Ltd. about the installation of special signal
receivers/transmitters allowing the mobile phone users to use their phones
inside the tunnel.
Mr. Praphat said the BMCL Co.
Ltd. has to install special equipment to allow the radio communications
between the police during emergencies inside the tunnel and the installation
of telecommunication special systems must be done by December 2002 for
the Northern section and the whole system by July 2003.
MRTA tunnel will be done by the end of February
2001
Thairath Daily, Saturday, November 18, 2000
Mr. Praphat Jongsa-nguan, MRTA director,
said that MRTA has nearly finished the tunnel construction. The first
drill of the last section from Samyan station to Hua Lamphong station
will be done on December 30, 2000 and the second drill of the section
will be done on February 25, 2001.
The MRTA Director said the contractor
have to dig Mahanakhon intersection to transport the equipment before
digging the last section and remove the drills after finishing the construction.
Therefore, it is necessary to make a detour from November 18, 2000 to
March 10, 2001.
Commentary by Wisarut: We hope that
the next government will make an immediate approval for the Southern extension
and the contractor who will handle this job for MRTA.
October 2000
Updates from Thai Newspapers
translated and summarized by Wisarut Bholsithi
MRTA and BMCL select Alstorm-Mitsubishi as
the producer of rolling stock for the MRTA Blue Line subway
Dailynews, BMA Section, September 8, 2000
At
4:30 PM on September 7, Mr. Prapaht Jong Sa-Nguan (MRTA Director) and
Mr. Plew Treewitsawawet (CEO of Ch. Karnchang PCL) announced to the press
that they have selected NESCO Co. Ltd., a Franco-Japanese consortium consisting
of Mitsubishi Corporation, Mitsubishi Electric Corporation, and Alstorm
Transports, as the provider of rolling stock to be used on MRTA Blue Line.
The ambassadors of France and Japan came to MRTA to witness this announcement.
Mr. Plew said Ch. Karnchang has selected
NESCO Co. Ltd. since the company offered the best deal in financial terms,
financial security, technical issues, maintenance, and quality assurance
with its 16 billion baht budget. NESCO will become 49% shareholder of
BMCL.
Mr. Plew said that BMCL was studying
in detail BTS passengers to obtain marketing data since the company has
seen that Skytrain carries much fewer passengers than expected. Nevertheless,
MRTA will offer a lower fare to attract more passengers. Furthermore,
MRTA will use a marketing campaign with a 15% lower fare during the first
months or even the first year of subway service (December 2002-December
2003).
Extensions are a very critical issue
to boost the number of passengers which requires strong and steady support
from the government.
Commentary by Wisarut: The discount during
the first year of service is a must indeed! I hope that NESCO won't
make the same blunder with vending machines that Siemens did. The vending
machines supplied by NESCO should accept 1-baht coins as well as 20 and
50-baht bills so passengers don't have to bother making change.
Still More September 2000 Updates from Thai
Newspapers
translated and summarized by Wisarut Bholsithi
MRTA Going Forward for Subway Southern Extension
Gives a chance for BMCL to get the Extension Concession
Dailynews, Bangkok Metro Section, August 28, 2000
MRTA is going forward
for the southern extension, waiting for the message from the Priority
Allocation Committee set up by Dr. Trairong. At the same time, MRTA has
a meeting with BMCL to discuss the plan to award the extension concession
to BMCL with a compromise that BMCL must buy more rolling stock and freeze
the fare rate at 14 to 38 baht level.
Mr. Praphat Jong Sa-Nguan, MRTA director, spoke
about about ACM Sombun's bad rap that MRTA would have to follow the steps
set by the law (actually budget constrains) by shortening the Southern
extension to Hualamphong-Tha Phra route. However, OCMLT suggested that
MRTA should extend to Bang Waek, 2 km more and total of 6 km so MRTA can
connect with other mass transit systems at the proposed Taksin Center.
MRTA is waiting for a consideration from the Priority Allocation Committee
set up by Dr. Tairong Suwannakhiree, Deputy PM. If the committee approves
their proposal, MRTA will forward the proposal to the Traffic Management
and eventually the cabinet to approve the construction.
Mr. Praphat said more about the extension plan
that the Southern extension would go from Hua Lamphong, pass the Yaowarat
area and Wang Boorapha area (Bangkok Chinatown and Bangkok Old Trade Center
respectively) which had limited space. Therefore, the single tunnel with
2 levels is a must since it is impossible to construct a double tunnel
in the same way as Bangsue-Hua Lamphong route (except at Silom Station)
has done. Furthermore, it requires a single tunnel with 2 levels across
Chao Phraya River before going aboveground after passing Tha Phra Intersection.
Therefore, the budget reduction for this extension
is very tough, if not impossible, to do due to the demanding tasks to
be carried out. MRTA demands 40 billion baht budget for civil engineering
work for this extension. The budget structure is the same old 80% from
public for structure construction and the other 20% from private for rolling
stock and services. For the concession, MRTA will simply ask BMCL to buy
more rolling stocks and freeze the fare rate at 14-38 baht to boost the
number of passengers due to expanding network.
Commentary by Wisarut: MRTA's hitting
the nail on the head! At least, this state enterprise has done the right
thing to expand southward even though it has to wait for approvals from
many agencies and eventually the cabinet. However, MRTA should quickly
gain R & D to enable the agency (and the contractors) to be able to
dig underground tunnels and lay subway tracks so it can make a joint venture
with SRT to dig subway tracks linking all 3 railway terminals in Bangkok
(Hua Lamphong, Bangkok Noy, and Wongwian Yai) together to turn Bangkok
into SEA transport hub.
September 2000
Updates from Thai Newspapers
translated and summarized by Wisarut Bholsithi
Mass Transit Systems to Work with MRTA Subway
Daily News, BMA Section, August 24, 2000
MRTA spending 70 million
baht to hire a consultant to analyze a plan to adjust all mass transit
systems to connect with the subway after the full operation begins in
2003. The analytical study will be completed in 14 months.
Mr. Praphat Jongsa-nguan, the MRTA director said
that MRTA had just signed a contract to hire Mushell Co. Ltd. to work
as a consultant for a study to connect MRTA with other mass transit systems
(actually other modes of land transportation) such as BMTA buses, Microbus,
taxi cabs, Skytrain, trains, and so on. The budget for this analytical
study is 70 million baht paid by JBIC. The study will start on September
1, 2000 and it will take 14 months to complete. During the study period
the consultant will report to MRTA from time to time.
Mr. Praphat said the study details will emphasize
on the rerouting of BMTA bus lines to prevent them from competing with
the MRTA subway since the MRTA fare is higher than the best BMTA buses
(14-38 baht for MRTA Blue Line vs. 8-18 baht for BMTA Euro-2 Air-conditioned
buses). Without the rerouting of BMTA buses, MRTA will have a huge loss
causing detrimental effects on other mass transit projects.
Commentary by Wisarut: It's about time
for MRTA, BTSC, BMTA, and OCMLT to discuss the plan to connect and enable
the passengers to use tickets to ride Euro-2 Air-conditioned buses and
then ride Skytrain and/or MRTA and vice versa. If the SRT successfully
revives the Hopewell project in 2007, another readjustment should be under
consideration. I hope that SRT will be able to revive Hopewell project
so the line will be the main mass transit route if Thailand is to become
a successful Olympic host in 2008. Otherwise, we have to wait until around
2020 to compete for a Olympic host again.
Sombun Fed Up with Chuan
Daily News, August 22, 2000
On August 21, 2000 at MRTA Office, there
was the 8th year anniversary ceremony for the MRTA establishment, which
Air Marshall Sombun Rahong, Ministry of the Prime Minister Office, takinf
charge of MRTA oversight.
Air Marshall Sombun spoke to MRTA officers
and contractors during the ceremony and at one point he rapped about Chuan
government: "This [Chuan] government pays no attention to the poor and
powerless but takes a great care of the rich and powerful! This government
is a totally stupid.... government.... [that] sells the nation off to
foreign imperialists since the government deliberately neglects the mass
transit system while other nations always take a great care with their
mass transit systems. No private sectors dare to invest in the mass transit
systems since they don't want to see their companies become bankrupt like
BTSC! Well, it sounds like I am blaming myself since I'm a part of this....
foolish government. I tried so hard to prevent the cabinet from making
stupid decisions [like rejecting the MRTA subway extension plan], but
they failed to hear my voice!"
Air Marshall Sombun told the corespondents the
construction the MRTA Blue line ran very well but it became impossible
to finish the Northern Extension (Bangsue-Phra Nanaklao Bridge) by 2004
and the Southern Extension (Hua Lamphong-Bang Kae) by 2005 since Chuan
and the Democrat cronies refused to acknowledge the critical matters of
the MRTA extension, thus they rejected the budget proposal for the MRTA
extensions.
Air Marshall Sombun agreed with Samak's
plan to extend the Skytrain and he wants the fare rate lowered so it does
not drive away the potential customers. He also said Samak knows so many
people--politicians and bureaucrats alike--and knows that he can stretch
the extensions as far as he wants. MRTA has no such a man so MRTA cannot
extend as long as it wants. Therefore, MRTA has to beg the upcoming government
to approve the extensions since Chuan government ran out of time.
August 2000
Updates from Thai Newspapers
Subway deal quietly pushed through
Concession terms fiercely criticised
Supoj Wancharoen, Bangkok Post,
August 2, 2000
The Metropolitan and Rapid Transit Authority
yesterday signed a multi-billion-baht subway concession contract with
Bangkok Metro Co Ltd. The signing was conducted quietly at the MRTA headquarters
with PM's Office Minister ACM Somboon Rahong, Ch Karnchang Plc chairman
Plew Trivisavavet and board members from the two firms present.
"That might be to avoid political criticism
because the project involves huge investment and has been under strong
attacks over its transparency in implementation. Also, the cabinet had
rejected the contract several times," an MRTA source said.
Chart Pattana ministers strongly opposed
the contract saying BMCL's 11.7-billion-baht contribution to the state
over 25 years was too low and its fare rate of 14-36 baht was too high.
BMCL deputy managing director Sompodh Sripoom
said his firm was about to choose a subway train supplier and that it
was negotiating with four companies on four criteria: finance, technology,
shareholding in BMCL and after-sale service.
BMCL wants a loan from its supplier and
the candidates will propose loans in different currencies, he said.
He said the train suppliers were in contact
for over a year and denied JBIC, a major creditor, was pressuring it to
pick up the Japanese supplier.
He said the supplier could be chosen in
the next few months and that part of the 20km subway, from Hua Lampong
to Bang Sue, could open in late 2002 with the full service opened in 2003.
The interested suppliers were the Alsthom
Group of France with a euro-and-yen loan of 19,036 million baht from the
French Coface export credit agency; the Bombardier Group of Canada with
a US-dollar loan of 19,321 million baht from Export Development Corp of
Canada; Germany's Siemens Group with a euro loan of 26,045 million baht
from KfW; and the JMC Group from Japan with a yen loan of 16,888 million
baht from Japan Bank for International Cooperation (JBIC).
June 2000
Updates from Thai Newspapers
translated and summarized by Wisarut Bholsithi
Proposal to extend subway rejected - MRTA told B40bn estimate too
high
Supoj Wancharoen - Bangkok Post, May 22, 2000
A government committee overseeing
mega transport projects has rejected a proposal by the Metropolitan Rapid
Transit Authority to spend 40 billion baht to extend the "blue line" subway
currently under construction to Tha Phra.
Committee sources said the
MRTA came under heavy criticism for trying to push through the proposal
at Friday's sitting chaired by Deputy Prime Minister Bhichai Rattakul.
The committee felt the proposed cost for the 6.4-km extension of the underground
railway was too high.
MRTA gave a breakdown of its
proposed investment as: 27 billion baht for design and civil work, three
billion baht for land expropriation, six billion baht for electrical installations
and four billion baht for other expenses.
ACM Somboon Rahong, deputy
prime minister supervising the MRTA, led other committee members in expressing
reservations over the cost.
He said the figure was too
high and the proposed budget for design and construction could be cut
by at least 20%, the sources said.
Kamroplak Surasawadee, deputy
director of the mega-project office, supported ACM Somboon's view.
He said it cost MRTA 24 billion
baht to build half of the 20-km Hua Lamphong-Bang Sue subway, known as
the blue line.
The proposed cost of the extension
could be cut by 25%, he was quoted as saying.
A Finance Ministry's representative
on the committee suggested that MRTA have talks with the National Economic
and Social Development Board to set a priority for the proposed extension
in comparison with other traffic projects.
The existing ceiling on the
volume of foreign loans which MRTA can raise should also be discussed
to avoid exacerbating the country's foreign debt.
MRTA director Prapat Chongsa-nguan
defended his proposal. He said the government should not be too concerned
with the size of the investment but should look at the economic return
the project could offer.
Compared to the economic loss
caused by traffic jams, the project was a worthwhile investment.
The cost of the proposed extension
was high because a section would have to pass under the Chao Phraya river.
His explanation failed to convince
the committee.
Mr Prapat was asked to review
his proposal and then resubmit it to the committee, the sources said.
MRTA also plans a northern
extension of the blue line subway.
Pathway designs to connect
MRTA and BTSC together have been completed
Dailynews, May 8, 2000
MRTA has finished designing
pathways to connected MRTA and BTSC together - with a reserved area for
BTSC to construct pathways along the rails later on.
MRTA director Mr. Praphat Jong
Sa-Nguan told the press that MRTA has finished the pathway design for
the connection at Silom station (MRTA). MRTA will have to use footpaths
and road surfaces around Silom Road to install escalators from the ground
levels to the station, and it will take three months to remove infrastructure
before the installation of escalators can begin. After that the
MRTA will erect pillars to support the construction and install a flyover
from Dusit Thanee to Robinson Department Store. There is no suitable
area to construct connecting pathways from Chulalongkorn Hospital even
though there is no problem finding an area to construct a flyover from
Dusit Thanee to Lumphinee Park.
MRTA Blue Line from Huay Kwang to Bangsue
will be opened first
Thaipost, May 22, 2000
MRTA director Prapat Chongsa-nguan
said that the construction of stations and tunnel is 62.09% complete.
The Hua Lamphong to Huay Kwang section has finished 66.83% of all work:
the main structure of all 9 stations in this section is done and now MRTA
is working on internal construction and the stairways. The tunnel digging
is 51.17% complete for the Southern section (7.628 km dug of 14.908 km)
- Rama IX to Sukhumvit section and Queen Sirikit National Convention Center
to Lumphinee section are dug. Now, MRTA is digging the tunnel from Sukhumvit
to Queen Sirikit National Convention Center and Lumphinee to Silom.
The Northern Section is 57.35% complete.
The main structures of almost all 9 stations are done. MRTA is constructing
ventilating rooms at the stairways. The tunnel in this section is 66.93%
complete (12.121 km dug of 18.110 km) - Tiam Ruammit to Suthisarn, Ratchada
to Phaholyothin, and Bangsue to Kamphaengphet are dug and Suthisarn to
Ratchada finished on May 17, 2000. MRTA is going to dig from Mochit to
Phaholyothin and open the Northern section (Huay Kwang to Bangsue) in
July 2002 and open all sections in July 2003.
May 2000
Updates from Thai Newspapers
translated and summarized by Wisarut Bholsithi
MRTA Proposes Southern Extension to the Cabinet and Talks with NESDB
to Clear the Hurdles that Delay the Project
Recently NESDB considered megaproject investments--80
projects so far--and created three classifications:
(1) Projects with the highest priority
(2) Projects with the secondary priority
(3) Approved projects with some management problems--10
projects--including the 70 billion baht project to extend the MRTA Blue
Line from Bangsue to Phranangklao Bridge
Mr. Praphat Jongsa-nguan, director of MRTA, said
he didn't feel sure if the news from NESDB about suspending the MRTA extension
projects follows the facts since MRTA Blue Line cannot become profitable
without northern and southern extensions and the cabinet has already approved
the construction of northern extension of the Blue Line.
Mr. Praphat said MRTA will send the guidelines
concerning the construction of the Southern extension from Hua Lamphong
to Tha Phra (a section from Hua Lamphong to Bang Khae) to the cabinet
for the approval. MRTA said the guidelines had been approved by the Large
Transportation Management Subcommittee and still need cabinet approval
to become effective.
Nevertheless, MRTA may send the plan back to
the NESDB to discuss the financial viability of this project.
The project is indeed expensive--even the expenditure
for laying tracks (25km) will cost 40 billion baht (US$1.1 billion). 10
billion baht (US$ 250-300 million) for the Northern extension (11.5km)
and 30 billion baht (US$750-800 billion) for the southern extension (13.5km).
(from Manager Daily, May 1, 2000)
Tunnel Digging to Connect BTSC and MRTA -
Police Worrying about Traffic Jam During the Construction
There was a discussion about the construction of underground
tunnels to connect BTSC and MRTA at Mochit and Civil Aviation Dept. on
April 25, 2000 at Metropolitan Police HQ. The proposed tunnel will be
120 m long and go along Phaholyothin and Kampahengphet Road. Construction
will start on April 28, 2000 and be finished around mid-July. The construction
will consume 3 lanes of road. Police said they feel so worried about traffic
jam during the rush hour--especially the outbound lanes of Kampahengphet
Road. They will resolve the problem by using reversible lanes--turning
two inbound lanes to two outbound lanes. The inbound will be jammed from
June 20-July 12 since the left side of the BTSC line will have one lane
left. Therefore, the police ask drivers to use Vibhavadee Highway and
Rama VI Road instead of Phaholyothin.
BMTA will also have to rearrange local bus stops as
follows:
1) Cancel the temporary bus stop at the corner of Chatuchak park and use
Chatuchak Weekend market stop and that opposite of TMB Bank from April
28 to June 3
2) Cancel the temporary bus stop at the corner of Chatuchak Weekend Market
and use Chatuchak Park stop and that opposite of TMB Bank from June 3
to June 13
3) Cancel the temporary bus stop at the corner of Chatuchak park and use
Chatuchak Weekend market stop and that opposite of TMB Bank from June
14 to June 19
4) Use all 3 bus stops from July 3 to 12
(from Daily News, April 26, 2000)
MRTA and BKT Meeting for the Tunnel Discussion
Royal Treasure Department, the owner of Mochit land,
will discuss with MRTA and BKT (Bangkok Terminal Co. Ltd.) land usage
for the construction of tunnels connecting the Skytrain and MRTA. MRTA
warns the Treasure Department that they will cancel the tunnel project
unless MRTA is allowed to use the Mochit area within a month.
MRTA told the reporters that the construction of Mochit
station (in Chatuchak Park) is nearly finished and the proposed tunnel
will end up in the Bangkok Terminal area - 6 m from the footpath. Unless
the tunnel construction begins within this month, the contractor will
have to wait and the MRTA will have to pay the workers even though there
is no work to do. If the Treasury Department allows MRTA to work
in the area, the tunnel construction will begin immediately.
(from Daily News, April 27, 2000)
April 2000
Updates from Thai Newspapers
translated and summarized by Wisarut Bholsithi
Police Concerned About Blind Spots in Subway Stations
The Metropolitan Police report
their concerns about telecommunication blind spots in subway stations.
They said they cannot use their radios to communicate with police stations
nearby or even with police HQ from the subway stations. These communication
blind spots will interfere with police ability to track down criminals
and assist crime victims - a very serious problem indeed!
Thus far, MRTA and the Police
Department have no solutions for the telecommunication blind spots yet.
IMHO, MRTA will have to install antenna in every station as well as in
the tunnels to enable police as well as passengers to communicate with
their comrades in other places (from Thai Post Daily, April 4,
2000).
Subway Operator Chosen
The Cabinet has approved BMCL (Bangkok Metro Co. Ltd.,
Subsidiary of Ch. Karnchang PCL) to become the private operator of MRTA
blue line despite strong protests from the Chart Patthana Party. However,
it is up to Office of the Attorney General to scrutinize the deal and
return the contract to the cabinet for final approval.
If the official contract is signed, Ch. Karnchang will
definitely choose Japan Metro Consortium as its partner in developing
the subway since Japan Metro proposed the lowest price and offered the
best financing terms of the four bidders. Also, Japan Metro has the best
technology and design and the German bidder (Siemens) could not compete
in terms of speed or electricity efficiency.
Those bidding for the partnership with Ch Karnchang
were:
1) Japan Metro (16.88 billion baht)
2) Alstom Transport and Mitsubishi Electric (19.036 billion)
3) Canada's Bombardier (19.32 billion)
4) Siemens (26.045 billion)
(from Thai Post and Bangkok Post)
March 2000
Updates from Thai Newspapers
translated and summarized by Wisarut Bholsithi
Presently, we are waiting until
there is a final solution to the conflicts between the BMCL (a private
firm with Ch. Karnchang as the major shareholder) or MRTA (State Enterprise
of the Prime Minister's office) - about who will buy trains and run the
services. This conflict also has caused a bit of a political rift between
the Democrats and Chart Phatthana parties since Chart Phathana said that
Ch. Karnchang paid less than what the TOR states in the contract (10 billion
baht from Ch. Karnchang vs. 24 billion baht from TOR) and the fare is
higher than what the TOR said (15-38 baht with inflation adjusted for
Ch. Karnchang vs. 14-36 baht with the ceiling of a 4% hike in the TOR).
The cabinet has to set up a committee to negotiate with Ch. Karnchang
so they can find a compromise for all parties involved in this project.
If negotiation fails, it will become necessary to call for a new bid or
the government will have to take over the whole project so they can control
the fare rate even though it would be counter to the privatization trend.
After that, we'll have to wait
to see who will be the supplier for the MRTA trains, Siemens (German firm)
or Kawasaki (Japanese firm). Siemens has an edge--it would be much easier
to integrate the fare and car system with BTS Skytrain
even though Ch. Karnchang prefers the Japanese firm which would cost 4-5
billion baht less than Siemens. from Thai Post Daily, January 18-21,
2000
The third hurdle for MRTA is
to have a fare to satisfy the firm who will run the subway as well as
Bangkokians. The BTS Skytrain
fare rate problems should give MRTA and the would-be subway operators
some lessons to ponder.
|